The invention provides a construction method for substation installation, which belongs to the field of construction engineering technology. The steps of the method include: dry transformer installation, transformer primary wiring, transformer accessories installation, 10 kV switchgear positioning, cabinet fixed installation, switchgear busbar installation, switchgear equipment debugging, low-voltage switchgear positioning, cabinet fixed installation, low-voltage switchgear busbar installation. Low-voltage switchgear commissioning, low-voltage bus positioning, low-voltage bus installation, equipment connection, equipment connection, cable bridge installation, bracket, suspension installation, cable bridge assembly and grounding, cable laying, commissioning power transmission scheme, electrical equipment adjustment test, single test of electrical equipment, group test, power transmission operation of electrical equipment. The installation and construction law of the substation regulates all links of construction, which ensures the construction sequence to be effectively guaranteed, the sequence is clear, the links, cooperation and transition between the front and back processes are good, and good cooperation procedures can be made in the field construction process.
【技术实现步骤摘要】
变电所安装施工工法
本专利技术涉及建筑工程
,具体地说是一种变电所安装施工工法。
技术介绍
一般的,变电所是电力系统中对电能的电压和电流进行变换、集中和分配的场所。为保证电能的质量以及设备的安全,在变电所中还需进行电压调整、潮流(电力系统中各节点和支路中的电压、电流和功率的流向及分布)控制以及输配电线路和主要电工设备的保护。变电所是电力网中的线路连接点,用以变换电压、交换功率和汇集、分配电能的设施。变电所中有不同电压的配电装置,电力变压器,控制、保护、测量、信号和通信设施,以及二次回路电源等。有些变电所中还由于无功平衡、系统稳定和限制过电压等因素,装设并联电容器、并联电抗器、静止无功补偿装置、串联电容补偿装置、同步调相机等。变电所主要设施包括配电装置、电力变压器、控制设备、保护自动装置、通信设施与补偿装置等。现有技术下的建筑工程针对10kV变电所的建筑施工环节不规范,不标准,施工顺序混乱,前后工序不衔接,没有良好的配合程序做现场指导。
技术实现思路
本专利技术的技术任务是解决现有技术的不足,提供一种变电所安装施工工法。本专利技术的技术方案是按以下方式实现的,该变电所安装施工工法,其特征在于该工法的步骤包括:干式变压器安装,变压器一次接线,变压器附件安装,10kV开关柜就位、柜体固定安装,开关柜母线安装、开关柜内设备调试,低压开关柜就位、柜体固定安装,低压开关母线安装,低压开关设备调试,低压母线定位,低压母线安装、设备连接,设备连接,电缆桥架安装,支、吊架的安装,电缆桥架的组装及接地,电缆敷设,冷缩电缆终端接头制作安装,剥切电缆,安装接地线,包绕填充胶,安 ...
【技术保护点】
1.变电所安装施工工法,其特征在于该工法的步骤包括:干式变压器安装,变压器一次接线,变压器附件安装,10kV开关柜就位、柜体固定安装,开关柜母线安装、开关柜内设备调试,低压开关柜就位、柜体固定安装,低压开关母线安装,低压开关设备调试,低压母线定位,低压母线安装、设备连接,设备连接,电缆桥架安装,支、吊架的安装,电缆桥架的组装及接地,电缆敷设,冷缩电缆终端接头制作安装,剥切电缆,安装接地线,包绕填充胶,安装三叉手套,安装绝缘套管,剥切金属屏蔽层、半导电、绝缘层,压接接线端子,安装冷收缩绝缘件,绕包绝缘带,冷缩电缆中间接头制作安装,电缆中间点定位、剥除电缆护层,剥切金属屏蔽层、半导电、绝缘层,套绝缘冷收缩管,导体连接,安装冷收缩接头主体,恢复金属屏蔽,安装外护套带,接地网安装、接地体连接,接地体埋设,接地线安装,接地电阻测量,电气试验,电力电缆试验,电缆测试,接地网试验,继电保护调试,二次回路绝缘试验,电压、电流互感器试验,二次回路检查,继电器、保护装置调试,整组试验、一次电流及工作电压检验,调试送电方案,电气设备调整试验,电气设备的单体试验,整组试验,电气设备的模拟试验,电气设备的送电运 ...
【技术特征摘要】
1.变电所安装施工工法,其特征在于该工法的步骤包括:干式变压器安装,变压器一次接线,变压器附件安装,10kV开关柜就位、柜体固定安装,开关柜母线安装、开关柜内设备调试,低压开关柜就位、柜体固定安装,低压开关母线安装,低压开关设备调试,低压母线定位,低压母线安装、设备连接,设备连接,电缆桥架安装,支、吊架的安装,电缆桥架的组装及接地,电缆敷设,冷缩电缆终端接头制作安装,剥切电缆,安装接地线,包绕填充胶,安装三叉手套,安装绝缘套管,剥切金属屏蔽层、半导电、绝缘层,压接接线端子,安装冷收缩绝缘件,绕包绝缘带,冷缩电缆中间接头制作安装,电缆中间点定位、剥除电缆护层,剥切金属屏蔽层、半导电、绝缘层,套绝缘冷收缩管,导体连接,安装冷收缩接头主体,恢复金属屏蔽,安装外护套带,接地网安装、接地体连接,接地体埋设,接地线安装,接地电阻测量,电气试验,电力电缆试验,电缆测试,接地网试验,继电保护调试,二次回路绝缘试验,电压、电流互感器试验,二次回路检查,继电器、保护装置调试,整组试验、一次电流及工作电压检验,调试送电方案,电气设备调整试验,电气设备的单体试验,整组试验,电气设备的模拟试验,电气设备的送电运行。2.根据权利要求1所述的变电所安装施工工法,其特征在于:该工法的步骤还包括:高压柜、低压柜、配电箱的安装,断路器安装,电缆、电线敷设,母线槽施工,设备点件检查,支架制作及安装,封闭插接母线安装,试运行验收,开关、插座、灯具安装。3.根据权利要求1所述的变电所安装施工工法,其特征在于:电气试验的步骤包括:变压器试验,10kV开关柜试验,断路器试验,电压互感器试验,电流互感器试验,开关柜的整体试验,避雷器试验。4.根据权利要求1所述的变电所安装施工工法,其特征在于:变压器一次接线:变压器进出线的支架与地网连接;电缆终端与引线可靠连接,搭接面清洁、平整、无氧化层,涂电力复合脂;插接式母线与变压器连接是软连接并应留有裕度;变压器本体接地线截面不小于中性线截面1/2;干式变压器的铁芯和金属件、带有防护罩干式变压器金属箱体的保护接地、变压器中性点接地线分别与电房主接地网独立连接,接地线两端用接线端子压接或焊接...
【专利技术属性】
技术研发人员:李应心,葛振刚,张爱军,胡杰,姜庆钢,张飞龙,郑华,郭鹏,陈梧江,李明辉,
申请(专利权)人:中建八局第一建设有限公司,
类型:发明
国别省市:山东,37
还没有人留言评论。发表了对其他浏览者有用的留言会获得科技券。