The invention discloses a construction method for synchronous sinking of jack of bridge double-wall steel cofferdam, which comprises the following steps: A. construction preparation, connecting water and electric pipeline of construction site of steel cofferdam, arranging construction site, preparing equipment, personnel allocation and construction materials, and analyzing engineering geology and construction materials in detail according to geological exploration data. Hydrogeological conditions, careful preparation of construction organization design, the establishment of construction monitoring plan; b, steel cofferdam design, according to the specific environmental design of double-wall steel cofferdam specific structure; c, steel cofferdam production, the whole cofferdam is made by on-site block processing. The beneficial effect is that the vertical connection of the steel cofferdam adopts the prestressed structure, and the separation work between the cofferdam above the river bed and the part below the river bed can be operated above the water surface, and the part above the river bed can be automatically raised to the water surface by the buoyancy of the water for demolition, without diving operation, and the demolition speed is fast, safe and economical. It is reliable.
【技术实现步骤摘要】
一种桥梁双壁钢围堰千斤顶同步下沉施工工法
本专利技术涉及水中钢围堰下沉和水中浮式沉井的施工
,特别是涉及一种桥梁双壁钢围堰千斤顶同步下沉施工工法。
技术介绍
近几十年来我国公路和铁路桥梁深水基础施工均大规模的采用双壁钢围堰作为临时挡水结构。传统的施工方法不仅浪费钢材,而且施工速度慢,需要施工人员潜到水下进行作业,危险性较高。为了提高施工速度和质量,减少施工投入,提高施工安全性,需要提供一种新型的桥梁双壁钢围堰千斤顶同步下沉施工工法。
技术实现思路
本专利技术的目的就在于为了解决上述问题而提供一种桥梁双壁钢围堰千斤顶同步下沉施工工法。本专利技术通过以下技术方案来实现上述目的:一种桥梁双壁钢围堰千斤顶同步下沉施工工法,包括如下步骤:a、施工准备,接接钢围堰施工现场水、电管线,布置施工现场,准备好机具设备、人员配置、施工材料,根据地质勘探资料详细分析了解工程地质和水文地质情况,认真编制施工组织设计,制定施工监测计划;b、钢围堰设计,根据具体的环境设计双壁钢围堰的具体结构;c、钢围堰制作,整个围堰全部采用现场分块加工制作;d、拼装平台搭建,将钢围堰的模块运输到桥墩承台的正上方,搭设临时首节围堰拼装平台;e、首节钢围堰拼装及下放平台搭建,在临时首节围堰拼装平台上进行首节围堰的拼装并搭建钢围堰下放平台;f、拆除拼装平台同时千斤顶下所述放首节钢围堰,拆除临时首节围堰拼装平台后在所述钢围堰下放平台上安装穿心千斤顶,并进行所述首节钢围堰的固定和下放;g、首节止水胶条安装,在所述首节钢围堰上安装所述止水胶条;h、第二节钢围堰精轧螺纹钢安装,在所述首节钢围堰上安装第二节精轧螺 ...
【技术保护点】
1.一种桥梁双壁钢围堰千斤顶同步下沉施工工法,其特征在于:包括如下步骤:a、施工准备,接接钢围堰施工现场水、电管线,布置施工现场,准备好机具设备、人员配置、施工材料,根据地质勘探资料详细分析了解工程地质和水文地质情况,认真编制施工组织设计,制定施工监测计划;b、钢围堰设计,根据具体的环境设计双壁钢围堰的具体结构;c、钢围堰制作,整个围堰全部采用现场分块加工制作;d、拼装平台搭建,将钢围堰的模块运输到桥墩承台的正上方,搭设临时首节围堰拼装平台;e、首节钢围堰拼装及下放平台搭建,在临时首节围堰拼装平台上进行首节围堰的拼装并搭建钢围堰下放平台;f、拆除拼装平台同时千斤顶下放所述首节钢围堰,拆除临时首节围堰拼装平台后在所述钢围堰下放平台上安装穿心千斤顶,并进行所述首节钢围堰的固定和下放;g、首节止水胶条安装,在所述首节钢围堰上安装所述止水胶条;h、第二节钢围堰精轧螺纹钢安装,在所述首节钢围堰上安装第二节精轧螺纹钢;i、钢围堰拼装、接高,将所述第二节钢围堰拼接安装在所述首节钢围堰上方;j、千斤顶进行预应力连接,将第二节钢围堰与所述钢围堰固定架固定在一起;k、拼装最后一节,在所述第二节钢围堰上方拼 ...
【技术特征摘要】
1.一种桥梁双壁钢围堰千斤顶同步下沉施工工法,其特征在于:包括如下步骤:a、施工准备,接接钢围堰施工现场水、电管线,布置施工现场,准备好机具设备、人员配置、施工材料,根据地质勘探资料详细分析了解工程地质和水文地质情况,认真编制施工组织设计,制定施工监测计划;b、钢围堰设计,根据具体的环境设计双壁钢围堰的具体结构;c、钢围堰制作,整个围堰全部采用现场分块加工制作;d、拼装平台搭建,将钢围堰的模块运输到桥墩承台的正上方,搭设临时首节围堰拼装平台;e、首节钢围堰拼装及下放平台搭建,在临时首节围堰拼装平台上进行首节围堰的拼装并搭建钢围堰下放平台;f、拆除拼装平台同时千斤顶下放所述首节钢围堰,拆除临时首节围堰拼装平台后在所述钢围堰下放平台上安装穿心千斤顶,并进行所述首节钢围堰的固定和下放;g、首节止水胶条安装,在所述首节钢围堰上安装所述止水胶条;h、第二节钢围堰精轧螺纹钢安装,在所述首节钢围堰上安装第二节精轧螺纹钢;i、钢围堰拼装、接高,将所述第二节钢围堰拼接安装在所述首节钢围堰上方;j、千斤顶进行预应力连接,将第二节钢围堰与所述钢围堰固定架固定在一起;k、拼装最后一节,在所述第二节钢围堰上方拼装最后一节钢围堰;钢围堰拼接完成、下放、就位,利用千斤顶控制柜控制所述穿心千斤顶启动带动双壁钢围堰整体下降;m、灌注双壁间砂砾、浇筑封底混凝土,在所述双壁钢围堰内部灌注砂砾并浇筑混凝土进行封底作业n、抽水、施工承台,抽出所述双壁钢围堰内部的积水,在所述双壁钢围堰内部施工承台o、拆除钢围堰,施工完成后拆除部分钢围堰,方便下次重复使用。2.根据权利要求1所述的一种桥梁双壁钢围堰千斤顶同步下沉施工工法,其特征在于:所述步骤a中的准备还包括混凝土原材料的实验,选定配合比后进行混凝土的生产。3.根据权利要求1所述的一种桥梁双壁钢围堰千斤顶同步下沉施工工法,其特征在于:所述步骤a中还包括施工用的钢材质量的检验。4.根据权利要求1所述的一种桥梁双壁钢围堰千斤顶同步下沉施工工法,其特征在于:所述步骤f中所述钢围堰下放平台下方设置有桩基钢护筒,将所述穿心千斤顶通过螺栓固定在所述钢围堰下放平台上方,在所述穿心千斤顶内安装高强钢绞线,然后将钢围堰固定架固定在所述...
【专利技术属性】
技术研发人员:姜振福,李付吉,康卫,
申请(专利权)人:中国建筑第四工程局有限公司,
类型:发明
国别省市:广东,44