The utility model discloses an open pit water storage system, which includes a work gang and a coal seam at the bottom of the work group. The work helps to set a number of steps on the steps, and the water storage tank is arranged on the steps, and the reservoir is extended along the direction of the coal seam. The utility model is implemented by setting a reservoir on the step of the work, extending the storage pool along the direction of coal seam and improving the storage capacity of the reservoir. At the same time, because the movement of the non working gang will not be confined to the reservoir, the non working gang can follow the advance of the working gang in time, reduce the stripping cost, and have nothing to do. It is necessary to change the location of the reservoir frequently and reduce the cost.
【技术实现步骤摘要】
一种露天矿蓄水系统
本技术涉及露天矿
,尤其涉及一种露天矿蓄水系统。
技术介绍
矿区内的水资源主要来自生产中的矿坑涌水,根据涌水量数据统计,平均年涌水量为300万立方米,平均月涌水量为25万立方米。矿区水资源的利用主要发生在夏季,夏季生产过程中的道路洒水降尘、复垦绿化中的灌溉等都会使用大量的水资源。现有的露天矿蓄水系统如图1所示,在用于进行土方剥离和开采煤矿的工作帮1′、以及用于进行排土的非工作帮2′之间设置蓄水池3′,现在的露天矿蓄水系统存在以下缺陷:1)蓄水能力低,由于受到运输成本限制,工作帮1′和非工作帮2′之间的距离不能相隔太远,导致蓄水池3′的蓄水能力有限,无法满足矿区在夏季大量用水的需求;2)增加剥离成本,由于蓄水池3′设置在工作帮1′和非工作帮2′之间,导致非工作帮2′无法及时跟进工作帮1′的推进,增大了剥离土方的运输距离,增加剥离成本;3)增加蓄水池的成本,由于需要尽量减小运输成本,所以当工作帮1′和非工作帮2′之间的距离达到上限时,废除原有的蓄水池3′,将非工作帮2′朝向采煤工作面移动,重新在工作帮1′和非工作帮2′之间设置新的蓄水池3′,通常每年需要重新设置两次以上蓄水池3′,增加成本。
技术实现思路
本技术的目的在于克服现有技术的露天矿蓄水系统蓄水能力低、成本高的不足,提供一种露天矿蓄水系统。本技术的技术方案提供一种露天矿蓄水系统,包括工作帮和位于所述工作帮的底部的煤层,所述工作帮上设置有多个台阶,所述台阶上设置有用于蓄水的蓄水池,所述蓄水池沿着面向所述煤层方向延伸。进一步的,所述台阶包括位于所述工作帮的底部的最下台阶,所述蓄水池设 ...
【技术保护点】
1.一种露天矿蓄水系统,包括工作帮和位于所述工作帮的底部的煤层,所述工作帮上设置有多个台阶,其特征在于,所述台阶上设置有用于蓄水的蓄水池,所述蓄水池沿着面向所述煤层方向延伸。
【技术特征摘要】
1.一种露天矿蓄水系统,包括工作帮和位于所述工作帮的底部的煤层,所述工作帮上设置有多个台阶,其特征在于,所述台阶上设置有用于蓄水的蓄水池,所述蓄水池沿着面向所述煤层方向延伸。2.如权利要求1所述的露天矿蓄水系统,其特征在于,所述台阶包括位于所述工作帮的起始端的最下台阶,所述蓄水池设置在所述最下台阶上。3.如权利要求2所述的露天矿蓄水系统...
【专利技术属性】
技术研发人员:张利忠,鞠兴军,张周爱,苏慎忠,金磊,
申请(专利权)人:中国神华能源股份有限公司,神华宝日希勒能源有限公司,
类型:新型
国别省市:北京,11