A pile foundation construction method is used in mud area. On the outside of the mud area, a main road is built along the bridge. From the main road to the mud area, a road road with a width of 10m is planned along each pile foundation. The height of the top surface is not less than the water level of the mud pool; the mud is solidified in the support Road area, and the mud curing range is extended to the side slope of the branch road and the side road of the ramp, and the depth of the curing layer is at least 3M. After the completion, a number of cement mixing piles and cement mixing pile are constructed down at the top of each branch road, and the cement mixing pile is built down at the top of each branch road. After completion of the construction and at least 28 days, the geotextile room on the top of the support road is set up and a slags layer with a thickness less than less than 80cm is filled, and the pile foundation is constructed with the support road as the construction platform.
【技术实现步骤摘要】
桥位处于泥浆区的桩基施工方法
本专利技术涉及桥梁施工
,具体涉及一种桥位处于泥浆区的桩基施工方法。
技术介绍
桥梁施工过程中,有时桥梁涉及位置要通过泥浆池或泥塘、沼泽等区域,无法在该区域直接进行桥梁桩基施工,需要对施工区的泥浆进行处理。对于大面积的泥浆区,如果将泥浆全部清理出去,不仅工程量大,而且堆放到别处也不符合环保要求;如果采用填筑的方法在直接泥浆区上方填筑土方,由于下部泥浆层较厚,地基松软,影响施工安全。针对上述问题,目前尚无妥善的解决办法。
技术实现思路
本专利技术的目的在于针对上述问题,提供一种安全、高效、环保的桥位处于泥浆区的桩基施工方法,并为今后同类工程区的施工提供借鉴。本专利技术的技术方案如下:一种桥位处于泥浆区的桩基施工方法,其特征在于,包括以下步骤:(1)修筑主便道,规划支便道:在泥浆区外侧,顺桥向修筑一条主便道,从主便道向泥浆区内,沿每一排桩基位置分别规划一条路面宽度为10m的支便道;(2)填筑支便道:根据规划的支便道区域向泥浆池内进行填土施工,每一条支便道填筑至顶面高度不低于泥浆池水位,填筑时支便道两侧按1:1.5放坡;(3)施工泥浆固化层:对支便道区域的泥浆进行固化处理,具体泥浆固化范围为支便道及支便道两侧边坡再向外延伸1m,设计固化层深度为至少3m;固化施工采用配备强力搅拌头的ALLU搅拌设备,采用垂直上下搅拌固化的方式,对设计固化范围的原位土进行搅拌,边搅拌边喷固化剂;(4)施工水泥搅拌桩:固化完成后,待支便道顶面形成一层硬壳,并且能承载水泥搅拌桩施工机械后,在每一条支便道顶部向下施工多个水泥搅拌桩,每个水泥搅拌桩的桩径为7 ...
【技术保护点】
一种桥位处于泥浆区的桩基施工方法,其特征在于,包括以下步骤:(1)修筑主便道,规划支便道:在泥浆区外侧,顺桥向修筑一条主便道,从主便道向泥浆区内,沿每一排桩基位置分别规划一条路面宽度为10m的支便道;(2)填筑支便道:根据规划的支便道区域向泥浆池内进行填土施工,每一条支便道填筑至顶面高度不低于泥浆池水位,填筑时支便道两侧按1:1.5放坡;(3)施工泥浆固化层:对支便道区域的泥浆进行固化处理,具体泥浆固化范围为支便道及支便道两侧边坡再向外延伸1m,设计固化层深度为至少3m;固化施工采用配备强力搅拌头的ALLU搅拌设备,采用垂直上下搅拌固化的方式,对设计固化范围的原位土进行搅拌,边搅拌边喷固化剂;(4)施工水泥搅拌桩:固化完成后,待支便道顶面形成一层硬壳,并且能承载水泥搅拌桩施工机械后,在每一条支便道顶部向下施工多个水泥搅拌桩,每个水泥搅拌桩的桩径为70cm,长度至少16m,并且保证深入泥浆层下方砂土层至少3m;相邻水泥搅拌桩的间距为2.8m,水泥搅拌桩位置与桥梁桩基位置冲突时,应避开桩基位置就近打设;(5)铺设宕渣层:水泥搅拌桩施工完成,并达到至少28天等强后,在支便道顶部设置土工格室, ...
【技术特征摘要】
1.一种桥位处于泥浆区的桩基施工方法,其特征在于,包括以下步骤:(1)修筑主便道,规划支便道:在泥浆区外侧,顺桥向修筑一条主便道,从主便道向泥浆区内,沿每一排桩基位置分别规划一条路面宽度为10m的支便道;(2)填筑支便道:根据规划的支便道区域向泥浆池内进行填土施工,每一条支便道填筑至顶面高度不低于泥浆池水位,填筑时支便道两侧按1:1.5放坡;(3)施工泥浆固化层:对支便道区域的泥浆进行固化处理,具体泥浆固化范围为支便道及支便道两侧边坡再向外延伸1m,设计固化层深度为至少3m;固化施工采用配备强力搅拌头的ALLU搅拌设备,采用垂直上下搅拌固化的方式,对设计固化范围的原位土进行搅拌,边搅拌边喷固化剂;(4)施工水泥搅拌桩:固化完成后,待支便道顶面形成一层硬壳,并且能承载水泥搅拌桩施工机械后,在每一条支便道顶部向下施工多个水泥搅拌桩,每个水泥搅拌桩的桩径为70cm,长度至少16m,并且保证深入泥浆层下方砂土层至少3m;相邻水泥搅拌桩的间距为2.8m,水泥搅拌桩位置与桥梁桩基位置冲突时,应避开桩基位置就近打设;(5)铺设宕渣层:水泥搅拌桩施工完成,并达到至少28天等强后,在支便道顶部设置土工格室,并填筑一层厚度不小于80cm的宕渣层;(6)以支便道为施工平台,在设计的桩基位置进行钢护筒打设,后续施工按普通桩基施工方式进行。2.根据权利要求1所述的桥位处于泥浆区的桩基施工...