Winter maintenance method of the invention, a short-term box girder construction method, belonging to the field of engineering construction, the steps of (1) concrete box girder, step (2) casting box girder roof insulation treatment, step (3) for casting box girder strength to meet the requirement, the casting box girder to the position. As the matching box girder, while pouring at repeat step (1), (2) making new casting box girder; step (4), box beam heat treatment, step (5) until the temperature reaches the insulation cover, the insulation cover, roof, multilayer box girder on thermal insulation removal, matching meet the room temperature after the lifting of the box girder, box girder after pouring new steps (3), as a new box girder, then repeat step (4), (5), thus completing the short line matching method of box girder construction in winter maintenance. By adopting the technical proposal, the surface of the box girder is not easy to generate shrinkage cracks, the quality is guaranteed, and the box girder is set in a reasonable and simple process during construction and maintenance, and the construction period is saved.
【技术实现步骤摘要】
一种短线匹配法箱梁施工的冬季养护方法
本专利技术涉及工程施工
,更具体地说,涉及一种短线匹配法箱梁施工的冬季养护方法。
技术介绍
混凝土施工中,工程质量受环境温度的限制,特别是冬季施工,由于环境温度低,对整个施工养护、质量等影响较大;混凝土浇注后其养护过程中应保证温度和湿度,如果保护措施不到位,受低温影响,水泥的水化作用受到阻碍,混凝土中的游离水分开始结冰,体积增大,则极易引起混凝土开裂,严重影响施工质量。当室外日平均气温连续5天低于5℃时,即属于冬季施工,我国北方地区海拔较高,气候干燥,常年有大风天气,冬季施工基础养护尤为关键。目前,冬季施工箱梁养护多采用搭建棚暖,并在暖棚内使用煤炉等加热升温,养护期间内需消耗大量的油、煤等燃料,同时需设置保湿设备保持暖棚内的湿度,增加了工作人员劳动强度,施工过程中存在一定的安全隐患,同时箱梁施工工期长,箱梁表面易产生裂纹,表面质量差。经检索,中国专利申请号:2012105847405,申请日:2012年12月30日,专利技术创造名称为:箱梁预制蒸汽养生设备及养生方法。我国北方冬季气温较低,但许多桥梁梁板预制限于工期要求,必须进行冬季施工。在低温状态下,混凝土形成的强度低,模板周转的日期长,不利于提高箱梁预制施工进度。该申请案的组成包括:箱梁,箱梁内部安装有蒸汽养生管、温控感应元件,蒸汽养生管通过蒸汽管道与蒸汽机连接,温控感应元件与温度仪表连接。该申请案用于箱梁预制蒸汽养生,但该申请案温控感应元件在潮湿环境易受影响,易对施工进度带来影响。中国专利申请号:2008100449994,申请日:2008年3月17日,专利 ...
【技术保护点】
一种短线匹配法箱梁施工的冬季养护方法,其特征在于:其是在短线匹配箱梁预制台座内的养护方法,其步骤如下:步骤(1)浇筑箱梁浇筑:在浇筑处进行浇筑箱梁浇筑,其浇筑箱梁模板均为钢模板,且钢模板外表面全覆盖有保温材料,同时在钢模板保温材料内插入温度计;步骤(2)浇筑箱梁顶板保温处理:在浇筑箱梁顶板进行多层保温处理,且在顶板与多层保温的棉被内插入温度计,对浇筑箱梁进行35h~40h的保温处理;步骤(3)匹配箱梁:待浇筑箱梁强度达到设计要求的50%后,拆除其上的钢模板,然后将浇筑箱梁移至匹配位置,作为短线匹配法施工的匹配箱梁,而在浇筑处重复步骤(1)、步骤(2)的操作制作新的浇筑箱梁;步骤(4)匹配箱梁保温处理:将匹配箱梁放入保温罩内,且利用额定功率为48KW的电蒸汽锅炉对匹配箱梁进行蒸汽保温,且在匹配箱梁的翼缘板、内腔内蒸汽达不到的地方悬挂温度计,待匹配箱梁强度达到设计要求的80%时,将通入保温罩内的蒸汽温度逐级变小,最后将电蒸汽锅炉关掉;步骤(5)匹配箱梁起吊:待保温罩内达到一定温度后,将保温罩去除,并将匹配箱梁顶板上的多层保温处理去除,待匹配箱梁的温度达到室温进行起吊后,将新的浇筑箱梁经过步 ...
【技术特征摘要】
1.一种短线匹配法箱梁施工的冬季养护方法,其特征在于:其是在短线匹配箱梁预制台座内的养护方法,其步骤如下:步骤(1)浇筑箱梁浇筑:在浇筑处进行浇筑箱梁浇筑,其浇筑箱梁模板均为钢模板,且钢模板外表面全覆盖有保温材料,同时在钢模板保温材料内插入温度计;步骤(2)浇筑箱梁顶板保温处理:在浇筑箱梁顶板进行多层保温处理,且在顶板与多层保温的棉被内插入温度计,对浇筑箱梁进行35h~40h的保温处理;步骤(3)匹配箱梁:待浇筑箱梁强度达到设计要求的50%后,拆除其上的钢模板,然后将浇筑箱梁移至匹配位置,作为短线匹配法施工的匹配箱梁,而在浇筑处重复步骤(1)、步骤(2)的操作制作新的浇筑箱梁;步骤(4)匹配箱梁保温处理:将匹配箱梁放入保温罩内,且利用额定功率为48KW的电蒸汽锅炉对匹配箱梁进行蒸汽保温,且在匹配箱梁的翼缘板、内腔内蒸汽达不到的地方悬挂温度计,待匹配箱梁强度达到设计要求的80%时,将通入保温罩内的蒸汽温度逐级变小,最后将电蒸汽锅炉关掉;步骤(5)匹配箱梁起吊:待保温罩内达到一定温度后,将保温罩去除,并将匹配箱梁顶板上的多层保温处理去除,待匹配箱梁的温度达到室温进行起吊后,将新的浇筑箱梁经过步骤(3)后移至匹配位置,作为短线匹配法施工的新的匹配箱梁,随后重复步骤(4)、步骤(5),从而完成整个短线匹配法箱梁施工的冬季养护。2.根据权利要求1所述的一种短线匹配法箱梁施工的冬季养护方法,其特征在于:所述步骤(1)中的保温材料为橡塑海绵。3...
【专利技术属性】
技术研发人员:夏辉,周桥,种爱秀,张六一,刘立海,杨康,孙发明,尤琦,
申请(专利权)人:中交二航局第四工程有限公司安徽分公司,
类型:发明
国别省市:安徽,34