The invention discloses a hanging basket cantilever construction method of cast-in-situ winter, the specific steps are as follows: (1) affixed to the external surface of flame retardant plastic extruded board hanging basket template; (2) flame retardant plastic extruded board layout outside hot water circulating pipeline; (3) the steel spot welding in the template is fixed on the crossbar rib plate and hot extrusion circular pipe; (4) cantilever segment adopts canvas wrapped; (5) an air gun to the beam formwork and reinforcement heating; (6) arrangement of temperature measuring points; (7) pouring concrete segment; (8) thin film and the quilt cover newly poured concrete beam; (9) T box girder structure the two cantilever end fire prevention board closure; (10) using coal stove heating in the cabinet, the electric steam generator to the indoor steam box; (11) tension grouting. The method of the invention has the advantages of simple steps, simple construction, easy construction, easy use, good use effect and high practical value.
【技术实现步骤摘要】
本专利技术涉及桥梁现浇箱梁施工
,具体是一种挂篮悬臂现浇冬季施工方法。
技术介绍
根据规范,当室外昼夜日平均气温连续5天稳定低于5℃时,即进入冬期施工。因为冬期挂篮悬浇施工的箱梁是一个位于高空不断移动的空间结构,混凝土运输和浇筑更困难,施工风险更大,投入更高。因此,需设计一种步骤简单、施工简便、经济性好、安全性高、施工质量易于保证的方法来保障冬期箱梁挂篮悬臂现浇的施工。
技术实现思路
本专利技术的目的在于提供一种综合了蓄热法、蒸汽加热法和暖棚加热法三种养护方式的挂篮悬臂现浇冬季施工方法。为实现上述目的,本专利技术提供如下技术方案:一种挂篮悬臂现浇冬季施工方法,其具体步骤如下:(1)挂篮模板翼缘板、侧模和底模的外表面粘贴阻燃挤塑板:阻燃挤塑板嵌入模板纵横肋之间;(2)阻燃挤塑板外侧布设热水循环管道:在阻燃挤塑板外侧以25cm间距布设热水循环管道,通过热水锅炉输送热水进行循环加热,保持模板外侧空间的温度;(3)通过将钢筋点焊在模板纵横肋上固定挤塑板和热水循环管道:采用Φ8钢筋与模板纵横肋点焊固定;(4)悬浇节段整体采用帆布包裹:悬浇节段模板外表固定好挤塑板和热水循环管道后,整体采用帆布包裹,保证箱梁节段的整体挡风效果,减少和外界空气的对流,确保新浇梁段的蓄热保温效果;(5)电热风炮对梁体模板和钢筋加热:确保混凝土在入模前模板、钢筋温度不低于5℃,此外,对上一节段悬臂端截面已浇筑混凝土表面用热水进行浇淋,保证该结合部温度在5℃以上;(6)布置测温点:混凝土浇筑前在箱梁内设置温度传感器作为测温点,测温点布置在保温最差部位,以备养护时对梁体混凝土进行温度监测,即 ...
【技术保护点】
一种挂篮悬臂现浇冬季施工方法,其特征在于,其具体步骤如下:(1)挂篮模板翼缘板、侧模和底模的外表面粘贴阻燃挤塑板:阻燃挤塑板嵌入模板纵横肋之间;(2)阻燃挤塑板外侧布设热水循环管道:在阻燃挤塑板外侧以25cm间距布设热水循环管道,通过热水锅炉输送热水进行循环加热,保持模板外侧空间的温度;(3)通过将钢筋点焊在模板纵横肋上固定挤塑板和热水循环管道:采用Φ8钢筋与模板纵横肋点焊固定;(4)悬浇节段整体采用帆布包裹:悬浇节段模板外表固定好挤塑板和热水循环管道后,整体采用帆布包裹,保证箱梁节段的整体挡风效果,减少和外界空气的对流,确保新浇梁段的蓄热保温效果;(5)电热风炮对梁体模板和钢筋加热:确保混凝土在入模前模板、钢筋温度不低于5℃,此外,对上一节段悬臂端截面已浇筑混凝土表面用热水进行浇淋,保证该结合部温度在5℃以上;(6)布置测温点:混凝土浇筑前在箱梁内设置温度传感器作为测温点,测温点布置在保温最差部位,以备养护时对梁体混凝土进行温度监测,即翼缘板左右侧各设置1个,顶板中设置1个,底板中设置1个,左右腹板处各设置2个,一组共计8个测温点,均采用测温线,腹板及底板测温线统一引到箱室内,顶板测 ...
【技术特征摘要】
1.一种挂篮悬臂现浇冬季施工方法,其特征在于,其具体步骤如下:(1)挂篮模板翼缘板、侧模和底模的外表面粘贴阻燃挤塑板:阻燃挤塑板嵌入模板纵横肋之间;(2)阻燃挤塑板外侧布设热水循环管道:在阻燃挤塑板外侧以25cm间距布设热水循环管道,通过热水锅炉输送热水进行循环加热,保持模板外侧空间的温度;(3)通过将钢筋点焊在模板纵横肋上固定挤塑板和热水循环管道:采用Φ8钢筋与模板纵横肋点焊固定;(4)悬浇节段整体采用帆布包裹:悬浇节段模板外表固定好挤塑板和热水循环管道后,整体采用帆布包裹,保证箱梁节段的整体挡风效果,减少和外界空气的对流,确保新浇梁段的蓄热保温效果;(5)电热风炮对梁体模板和钢筋加热:确保混凝土在入模前模板、钢筋温度不低于5℃,此外,对上一节段悬臂端截面已浇筑混凝土表面用热水进行浇淋,保证该结合部温度在5℃以上;(6)布置测温点:混凝土浇筑前在箱梁内设置温度传感器作为测温点,测温点布置在保温最差部位,以备养护时对梁体混凝土进行温度监测,即翼缘板左右侧各设置1个,顶板中设置1个,底板中设置1个,左右腹板处各设置2个,一组共计8个测温点,均采用测温线,腹板及底板测温线统一引到箱室内,顶板测温线由顶板引出;(7)浇筑节段混凝土:混凝土浇筑选择在白天温度较高时段进行,有利于混凝土入模温度的控制;(8)薄膜及棉被覆盖新浇梁段混凝土:针对箱梁翼缘板处结构较薄容易散热受冻,在翼缘板顶面先覆盖一层塑料薄膜,再在其上加装电热毯,然后覆盖棉被,以加强翼缘板部位保温;(9)箱梁T构两悬臂端采用防火岩棉板封堵;(10)在箱室内采用煤火炉升温,同时采用电蒸汽发生器向箱室内输送蒸汽:共计4台煤火炉,每天煤火炉顶放置一个不锈钢水桶,起到加湿和升温作用;浇筑后箱室内持续加热和蒸养,保证温度的同时用蒸汽提供湿度,确保箱内温度不低于5℃,并保持箱室内温度基本恒定;为了防止煤气中毒和二氧化碳浓度过高加速混凝土的碳化,务必把火炉的排气管引出箱室外;(11)张拉压浆:挂篮节段混凝土强度达到设计要求后进行张拉压浆,压浆拌合用水采用搅拌...